Short answer:a swimming pool installation runs in seven steps: a first conversation with photos and dimensions, a site survey, design and quotation, contract and approvals, the build itself, commissioning and handover, then aftercare. For an outdoor concrete pool the build typically takes 8–14 weeks on site, but the steps before it decide how smoothly it goes.
Key takeaways
The first step is a conversation: photos and rough dimensions of your space tell us a lot before anyone visits.
A site survey checks access, ground conditions, services and planning constraints.
A fixed design and written quotation come before any contract is signed.
On site, an outdoor pool typically takes 8–14 weeks and an indoor or basement pool 14–22 weeks.
Handover includes a walk-through of the controls, water care and seasonal maintenance.

Step 1: The first conversation
Most projects start with a call or an email. If you send photographs and approximate dimensions of the space, we can give an early view of what is possible, the likely type of pool and a realistic budget range. This saves time on both sides and means the first meeting is focused on your project.
Step 2: Site survey
The survey looks at the things that shape every pool installation: access from the road, ground conditions and groundwater, trees and roots, drainage, existing services, neighbouring structures and any planning constraints such as a listed building or conservation area.
Step 3: Design and quotation
We develop the layout, size, depth, edge detail, steps, finishes, heating, filtration and lighting. For bespoke projects this includes 3D visualisation, so you can see the pool before it is built. The design is then priced as a written quotation with a clear scope, so you know exactly what is and is not included.
Step 4: Contract, approvals and programme
Once you are happy with the design and price, the contract sets out the scope, programme, payment stages and guarantees. Any approvals come next: a Lawful Development Certificate or planning application if needed, building regulations for pool buildings, and party wall notices where excavation is close to a neighbour. The build slot is then booked.
Step 5: The build
On site, the work follows a fixed sequence: excavation, steel reinforcement, the concrete shell, curing, waterproofing, a 72-hour water test, then tiling, coping and plant room fit-out. We explain each stage in detail in our guide tohow a reinforced concrete pool is built.

Step 6: Commissioning and handover
The pool is filled, the water balanced and the plant run in. At handover we walk you through the controls, the cover, water care and what to do as the seasons change, and give you the documents you need, including electrical certification and your structural guarantee.
Step 7: Aftercare
A pool needs regular water care and periodic servicing of pumps, filters and heaters. We give you a clear maintenance routine at handover and remain available for advice once you are swimming.
How long does a swimming pool installation take overall?
From first conversation to first swim, allow several months. Survey, design, quotation and approvals often take as long as the build. On site, an outdoor concrete pool typically takes 8–14 weeks and an indoor or basement pool 14–22 weeks.
How you can help the project run smoothly
Agree where the site compound, skips and spoil will go before work starts.
Talk to your neighbours early, especially if access, noise or deliveries will affect them.
Keep a clear route for excavators and concrete pumps, and protect drives and lawns along it.
Make decisions on tiles, coping and lighting before the shell is built, because fittings are cast into the concrete.
Plan how children and pets will be kept away from the excavation.
What happens to the excavated soil?
Digging a pool produces a large volume of spoil. Some can be reused to shape the garden, but most is usually taken away by grab lorry or skip, and that cost and route belong in the quotation. Ground conditions, such as London clay or a high water table, also affect how the excavation is supported and pumped during the build.
Living with a building site
Most installations involve a few weeks of heavy work, mainly during excavation and concreting, followed by quieter weeks of waterproofing, tiling and plant installation. Working hours, deliveries and parking are agreed before the start, and the site is kept tidy and secure at the end of each day. If you plan to be away, agree how you will receive updates and approve decisions. Photographs and short weekly updates help you follow progress.

Frequently asked questions
What is the first step in installing a swimming pool?
Start with a conversation. Sending photographs and approximate dimensions of the space lets a pool company give an early view of what is possible and a budget range before a survey is arranged.
How much disruption does a pool installation cause?
The heaviest disruption is during excavation and concrete work, when machinery and deliveries are on site. A good contractor plans access, spoil removal and working hours to keep disruption to neighbours and the household to a minimum.
Do I need to be at home during the installation?
Not every day. Most clients are on site at key points, such as setting out, decisions on finishes and handover, while regular progress updates cover the rest.
What is included in a swimming pool installation quote?
A clear quotation should list the pool structure, waterproofing, finishes, heating, filtration, lighting, cover, electrics, paving and any building work, and state what is excluded. Compare quotes on the same scope, not just the headline price.
Do I need planning permission to install a pool?
Often not. Planning Portal guidance says many outdoor domestic pools can be built under permitted development, as long as they meet the limits and conditions for outbuildings. Listed buildings, conservation areas, National Parks and other designated land are different, and pool buildings and basements bring their own rules, so we check this at survey stage.
Sources and references
Talk to us about your pool
See ourswimming pool installation page. Book a free consultation, or email photographs and dimensions of your space toinfo@swimmingpoolcompany.co.ukfor an initial assessment.
Book a free consultation with The Swimming Pool Company London
The Swimming Pool Company has designed and built bespoke reinforced concrete pools across London and the South East since 2011. More than 50 London families now swim in pools we've built, and every one is backed by a 10-year structural guarantee.
If you're thinking about a pool, start with a free consultation. Send us a few photos of your garden and its rough dimensions, and we'll talk you through what's possible, what to check first and how to turn your idea into your dream pool and dream design.
Call: 0208 058 0871
Email: info@swimmingpoolcompany.co.uk
Visit: 87 Notting Hill Gate, London W11 3JZ
Book your free consultation
If you are still at the planning stage, speak to a specialist swimming pool company in London before you dig. The decisions made now are the ones that are hardest to change later.
Published on 22 November 2026 by The Swimming Pool Company.