By The Swimming Pool Company | Published 12 November 2026

A reinforced concrete swimming pool is built in nine main stages: design and survey, setting out and excavation, steel reinforcement, the concrete shell, curing, waterproofing, a 72-hour water test, tiling and finishes, then commissioning. For an outdoor pool the site work typically takes 8–14 weeks once design and approvals are complete.
Swimming pool construction starts long before the digger arrives: survey, design and approvals set the programme.
We build shells in C35/45 water-resistant concrete around a fixed steel reinforcement cage.
A multi-layer cementitious waterproofing system goes on before any tile, and is proved with a 72-hour water test.
Tiles are fixed with EN 12004 adhesives, double-buttered for at least 95% coverage.
Outdoor pools typically take 8–14 weeks on site; indoor and basement pools 14–22 weeks.
Stage 1: Survey and design
Every concrete pool starts with the ground and the access. We check soil conditions, groundwater, trees, drainage routes, neighbouring foundations and the route from the road to the garden. The design fixes the size, depth profile, edge detail (skimmer, deck-level or vanishing edge), steps, plant room location and finishes. Structural calculations and any planning or party wall matters are settled here, because changing them once the shell is cast is slow and expensive.
Stage 2: Setting out and excavation
The pool is marked out on site and levels are taken from a fixed datum. Excavation follows, with spoil removed by grab lorry or skip; in London, a narrow side passage often means a mini-digger and conveyor. The hole is dug slightly larger than the finished pool to allow working space, and any groundwater is managed before the base goes in.
Stage 3: Base and steel reinforcement
A blinding layer of concrete gives a clean, level working surface. Steel reinforcement bars are then fixed into a cage that follows the floor and walls, with the cover and spacing set by the structural engineer. Pipework for main drains, returns and any lighting is positioned at this stage so it is cast into the structure rather than cut in later.
Stage 4: Pouring or spraying the concrete shell
The shell is formed in C35/45 water-resistant concrete, either cast into formwork or sprayed. Getting full compaction around the steel and pipework matters more than speed: voids and cold joints are where leaks begin. For a vanishing edge or deck-level pool, the weir and overflow channels are formed with particular care, because a few millimetres of error shows on the waterline.
Stage 5: Curing
Concrete gains strength over weeks, not days. The shell is kept damp and protected while it cures, so it does not crack as it dries. Rushing this stage to save a week is a false economy.

Stage 6: Waterproofing
We apply a multi-layer cementitious waterproofing system to the inside of the shell, with reinforcing tape at joints and around every fitting. The concrete does the structural work; the waterproofing makes sure the pool holds water for decades. That is why we treat the shell and waterproofing as one system and back it with a 10-year structural guarantee.
Stage 7: The 72-hour water test
Before a single tile is fixed, the pool is filled and monitored for 72 hours. Our benchmark is a loss of under 2–3mm a day once evaporation is accounted for. If the test is not passed, the cause is found and fixed while the shell is still bare. Testing before tiling is the single most important quality check in concrete pool construction.
Stage 8: Tiling, coping and finishes
Once the test is passed, the pool is drained and tiled. We fix mosaic, porcelain or stone with EN 12004 adhesives, double-buttered for at least 95% coverage so there are no hollow spots behind tiles. Coping stones, surrounding paving and any deck-level grilles follow.
Stage 9: Plant, commissioning and handover
The plant room is fitted out with pump, filter, heater, dosing and controls, and electrical work is certified to BS 7671. The pool is filled, balanced and run in. At handover we walk you through the controls, cover, water care and seasonal maintenance.

A real example: a vanishing edge in Henley-on-Thames
Ourvanishing edge pool in Henley-on-Thamesshows why each stage matters. A vanishing edge only works if the weir is perfectly level and the catch channel and balance tank are sized correctly, all of which is decided in design and built into the concrete shell.
Why we water-test before tiling
Testing the shell with water before any tile is fixed means a defect is found while it is easy to reach and repair. Once the pool is tiled, a leak is far harder to trace and more expensive to fix, which is why the water test is a fixed stage in every build.
Frequently asked questions
How long does it take to build a concrete swimming pool?
On site, an outdoor concrete pool typically takes 8–14 weeks and an indoor or basement pool 14–22 weeks. Survey, design and any approvals come before that, and weather, access and ground conditions can extend the programme.
Why is a 72-hour water test important?
It proves the shell and waterproofing hold water before the tiles hide them. Finding and fixing a leak in a bare shell is quick; finding one behind finished tiles means taking the finish off. Our benchmark is a loss of under 2–3mm a day.
What concrete is used for swimming pools?
We use C35/45 water-resistant concrete for the shell, reinforced with a steel cage designed by a structural engineer. The concrete gives strength and durability, and a separate cementitious waterproofing system makes the pool watertight.
Can you build a concrete pool with poor access?
Usually, yes. Unlike a one-piece fibreglass shell, a concrete pool is built piece by piece, so materials can come through a narrow side passage, and spoil can leave by conveyor or small machinery.
How long does a concrete pool last?
A well-designed and well-built reinforced concrete pool can last for decades. Finishes, equipment and some waterproofing details may need refurbishment over time, but the structure is built for the long term, and ours carries a 10-year structural guarantee.
Sources and references
BSI, BS 8102:2022 Protection of below ground structures against water ingress
Talk to us about your pool
See ourswimming pool installation pagefor how we run a build. Book a free consultation, or email photographs and dimensions of your space toinfo@swimmingpoolcompany.co.ukfor an initial assessment.
Book a free consultation with The Swimming Pool Company London
The Swimming Pool Company has designed and built bespoke reinforced concrete pools across London and the South East since 2011. More than 50 London families now swim in pools we've built, and every one is backed by a 10-year structural guarantee.
If you're thinking about a pool, start with a free consultation. Send us a few photos of your garden and its rough dimensions, and we'll talk you through what's possible, what to check first and how to turn your idea into your dream pool and dream design.
Call: 0208 058 0871
Email: info@swimmingpoolcompany.co.uk
Visit: 87 Notting Hill Gate, London W11 3JZ
Book your free consultation
If you are still at the planning stage, speak to a specialist swimming pool company in London before you dig. The decisions made now are the ones that are hardest to change later.